I-10 Tippecanoe Ave Interchange Improvements (Phase 1)

Description: In the cities fo San Bernardino and Loma Linda, from Waterman Avenue to Tippecanoe Avenue. Widen eastbound Tippecanoe Avenue off ramp and widen eastbound I-10 to provide four mixed flow lanes and on

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Loma Linda
Zip Code
 
Senate District
29
Assembly District 62, 63
Congressional District 43
 
Caltrans District
08
 
 
County/State Route San Bernardino 10
Postmile Begin/End 25.3 26.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  14571    40  
Lane Miles Added (Mixed)      0.85  
Peak Period Time Savings (minutes)  268060    600  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
San Bernardino Associated Governments (SANBAG) Barbara Fortman (909)884-8276   Bfortman@sanbag.ca.gov
Design (PS&E) Phase
San Bernardino Associated Governments (SANBAG) Barbara Fortman (909)884-8276   Bfortman@sanbag.ca.gov
Right of Way Phase
San Bearnardino Associated Governments (SANBAG) Barbara Fortman (909)884-8276   Bfortman@sanbag.ca.gov
Construction Phase
San Bernardino Associated Governments (SANBAG) Barbara Fortman (909)884-8276   Bfortman@sanbag.ca.gov
 
Corridor System Management Plan
San Bernardino Associated Governments (SANBAG) Andrea Nieto (909) 884-8276   anieto@sanbag.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$10,000 $0 $10,000
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$5,833 $2,787 $8,620
Non Budgeted ETC
$0 $0 $0
 
Total**** $15,833 $2,787 $18,620

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,242 $0 $1,242 $0
Design(PS&E)
$1,581 $0 $1,581 $0
Right of Way
$10 $0 $10 $469
Construction
$13,000 $2,787 $15,787 $16,693
 
Total* $15,833 $2,787 $18,620 $17,162

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/19/2005 

01/27/2011 
 

 
12/19/2005 

01/27/2011 
100  12/19/2005 

01/27/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/03/2008 

03/28/2012 
 

 
12/03/2008 

03/28/2012 
100  12/03/2008 

03/28/2012 


Begin Right of Way Phase

End Right of Way Phase
01/27/2011 

01/11/2012 
 

 
01/27/2011 

01/11/2012 
100  01/27/2011 

01/11/2012 


Begin Construction Phase

End Construction Phase
07/11/2012 

07/11/2013 
 

 
07/11/2012 

07/11/2013 
100  07/11/2012 

03/09/2015 


-20 
Begin Closeout Phase

End Closeout Phase
08/01/2013 

08/01/2015 
 

 
08/01/2013 

08/01/2015 
100  03/10/2015 

07/31/2015 
-20 

Corridor System Management Plan
Adoption Date 06/01/2011    06/01/2011  06/01/2011 
Implementation Date 08/01/2011    08/01/2011  08/01/2011 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 14571 40
Lane Miles Added (Mixed) 0.85
Peak Period Time Savings (minutes) 268060 600

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$10,000,000
Actual Expenditures:
$10,000,000

 

Status as of December 31, 2023.